Harbor Springs School District
Blackbird Elementary
Shay Elementary
Harbor Springs Middle School
Harbor Springs High School
HSPS Home
Superintendent
Directory
Board of Education
School Calendar
Enrollment
PTO
Human Resources
Community Pool
Community
Performing Arts Center
School Closing Procedures
Food Service
Band
Athletics
Technology
Media Center
Maps to HSPS
Contact Us

PowerSchool - Parent/Student

PowerSchool Teacher Portal

Community Pool > Pool Renovation Project

Update Friday, September 5th


This page is dedicated to the pool renovations.  Weekly pictures will be taken on the progress of the renovations to the lights, deck and ventilation system.  The pool will be drained on Wednesday, June 4th, which should take three days, and equipment will be removed in order for demolition to begin on Monday, June 9th. 

Items up for renovation will include:

  • New Underwater and Overhead Lights
  • New Tiled Deck
  • New Ventilation System and Duct Work
  • New Doors
  • Reconfiguration of the old Weight Room
  • Entrance to the Pool

The pool before renovations begin

May 31st

The draining process begins at 12:00 pm, June 4th

160,000 gallons of water is drained in less than 24 hours

 

          

   Thanks to some rain, work moved inside and           Removal of old deck began on

 the half wall was removed on Thursday, June 5th              Monday, June 9th

 

         

The ventilation system is removed on Wednesday and Thursday, June 11th and 12th

 

June 16th - 20th progress

         

Removal of the old ventilation system is complete        A new wall is installed in the old weight room

         

    Concrete was poured on June 20th for                      Backfilling around the new weight room

             the new weight room floor                                              and pool entrance

        

                                            Progress on removing the pool deck

June 23rd - 27th progress

         

  The final section of the old deck is removed         It was discovered that several areas of concrete

                                                                         will have to be replaced before the new tile can

                                                                         be put down.

      Progress on the new weight room

June 30th - July 4th progress

          

      The doors and frames are removed                 The deck material is removed from the windows

         

                                 The new entrance to the weight room and pool             

July 7th - 11th progress

                                                        Removing the bad sections of concrete 

                                                             More concrete being removed                  

         

                                        All of the rusted conduit needs to be replaced

July 14th - 18th progress

        

              All of the concrete with the exception of the south end needed to be removed

                          

                  Just about all of the conduit and wiring is removed

       

         The electricians begin work                             The east wall bench needed to be removed

                 

     The final sections of concrete are removed and they begin filling in the old ventilation duct

July 21st - 25th progress

       

                                   Work begins on the ventilation system

                    

                                  Work is wrapping up on laying the new conduit

                  

                        The anchors are in place and waiting for the concrete to be poured

     

               The deck drains are in place                         The roof to the weight room is put on

July 28th - August 1st

       

              Prep work on the deck begins for pouring the concrete on Thursday

       

                   The pump truck pumps in roughly 8 trucks loads of concrete

      

The concrete is drying and work will begin on       Concrete is being poured on the 2nd floor of the

  on the ventilation duct work on Monday                              new weight room

August 4th - 15th

       

                         The new ventilation duct work is being installed

                  

     Work is wrapping up on the exterior brick to the weight room and entrance to the pool

August 18th - 22nd

       

       The ventilation duct work is wrapping up with work on the lighting beginning next week

August 25th - September 5th

                      

                       Work is wrapping up on the new entrance and weight room

       

 The new duct work is completed and painted              Prep work begins on the deck tile

                            

The new ventilation system is delivered and scheduled to be installed on Monday, September 8th

 

Harbor Springs School District | Blackbird Elementary | Shay Elementary | Harbor Springs Middle School | Harbor Springs High School
About HSPS | Superintendent | Weekly Editorials | Directory | Board of Education | School Calendar | Enrollment | PTO | Employment | Community Pool
Community Schools | Performing Arts Center | School Closing Procedures | Food Service | Band | Athletics | Technology | Media Center | Maps to HSPS | Contact Us

©Harbor Springs Public Schools
Website by Mintaka Design

All photos are copyright Harbor Springs Public Schools or Mintaka Design unless otherwise indicated and may not be used without written permission.