Concrete was poured on June 20th for Backfilling around the new weight room
the new weight room floor and pool entrance
Progress on removing the pool deck
June 23rd - 27th progress

The final section of the old deck is removed It was discovered that several areas of concrete
will have to be replaced before the new tile can
be put down.

Progress on the new weight room
June 30th - July 4th progress

The doors and frames are removed The deck material is removed from the windows

The new entrance to the weight room and pool
July 7th - 11th progress
Removing the bad sections of concrete
More concrete being removed

All of the rusted conduit needs to be replaced
July 14th - 18th progress

All of the concrete with the exception of the south end needed to be removed
Just about all of the conduit and wiring is removed

The electricians begin work The east wall bench needed to be removed

The final sections of concrete are removed and they begin filling in the old ventilation duct
July 21st - 25th progress

Work begins on the ventilation system

Work is wrapping up on laying the new conduit
The anchors are in place and waiting for the concrete to be poured

The deck drains are in place The roof to the weight room is put on
July 28th - August 1st

Prep work on the deck begins for pouring the concrete on Thursday

The pump truck pumps in roughly 8 trucks loads of concrete
The concrete is drying and work will begin on Concrete is being poured on the 2nd floor of the
on the ventilation duct work on Monday new weight room
August 4th - 15th

The new ventilation duct work is being installed
Work is wrapping up on the exterior brick to the weight room and entrance to the pool
August 18th - 22nd
The ventilation duct work is wrapping up with work on the lighting beginning next week
August 25th - September 5th
Work is wrapping up on the new entrance and weight room

The new duct work is completed and painted Prep work begins on the deck tile

The new ventilation system is delivered and scheduled to be installed on Monday, September 8th
September 7th - 12th

The new ventilation system is moved into place and work begins on hooking it up

The first of 32 new overhead lights is installed and tested

Prep work for the new tile is wrapping up

One more corner to complete and then the new tile will go down next week
Getting rid of the old sand and getting ready to install the new filters
September 15th - 19th
The new tile is being installed along the east side (bleacher side)

The new underwater lights get installed The new tile goes in along the shallow end

The bleachers get put back on deck and reassembled
September 22nd - 26th

Two new filters get installed The trim work on the tile begins

The last section of tile to be installed is Workers begin grouting the office
around the hot tub
September 29th - October 3rd

The cleaning process begins

The painters began this week The electricians continue to install the new lights

The first half of the lights and installed and tested
October 6th - 10th

The pool begins to be filled on Tuesday The pool is full on Wednesday

The test run on the new ventilation system took place on Thursday
and the painters finished up with the doors
November 3rd - 14th
The new scoreboard gets installed Some minor touch ups and we are open for business

The first time in over 15 years all of the 1st one in the water in 6 months
underwater lights work

The weight room is completed and ready for use

Thank you for your patience during this time and we hope you enjoy the new facilities
|